Gundagai Sewage Treatment Plant

Location: Gundagai, NSW

Customer: Cootamundra-Gundagai Regional Council

The new plant will meet projected increases over the next 30 years. The new biological treatment is based on the Intermittently Decanted Extended Aeration (IDEA) treatment process, to which micro-organisms contained within the sewage treatment process, aid to break down organic matters. Management of the treated effluent continues via the existing effluent reuse system with remaining excess (if any) to discharge into the Murrumbidgee River. Due to the out-date plant Inland Power Solutions were able to install 500Kva to power the new plant.

Scope of work:

  • Relocate and remove overhead high voltage powerline from the treatment plant site
  • Install 400m of underground high voltage cable
  • Install 500KVA Pad mount Substation on culvert footing

 

Gallery

Enquiry

T. 02 6925 0041